Reconstruction work begins at Hillview

Phase 1 of the reconstruction of Hillview Middle School has begun on the campus at the corner of Santa Cruz and Elder avenues.

In an interview, Ahmad Sheikholeslami, district director of facility planning and construction, said the first phase will include the removal of the tennis courts, Tinker Park, the basketball courts, the open field and the parking lot.

Mr. Sheikholeslami estimated that Phase 1 will last four or five months, at which time the district will put out another bid for the actual construction of the school.

The goal is to have the work done on weekdays during normal working hours, though there may be "crunch times," Mr. Sheikholeslami told The Almanac. "If we're going to work on Saturdays, we will let our neighbors know."

To contact Mr. Sheikholeslami with questions or concerns, call 321-7140 and press option 2.

Comments

There are no comments yet for this post

Post a comment

Posting an item on Town Square is simple and requires no registration. Just complete this form and hit "submit" and your topic will appear online. Please be respectful and truthful in your postings so Town Square will continue to be a thoughtful gathering place for sharing community information and opinion. All postings are subject to our TERMS OF USE, and may be deleted if deemed inappropriate by our staff.

We prefer that you use your real name, but you may use any "member" name you wish.

Name: *

Select your neighborhood or school community: * Not sure?

Choose a category: *

Since this is the first comment on this story a new topic will also be started in Town Square! Please choose a category that best describes this story.

Comment: *

Verification code: *
Enter the verification code exactly as shown, using capital and lowercase letters, in the multi-colored box.

*Required Fields