Valparaiso roadwork almost done

Original post made by Andrea Gemmet, Almanac staff writer, on Feb 22, 2007

The town's roadwork on Valparaiso Avenue, between El Camino Real and University Drive, could be finished as early as next week, said Duncan Jones, Atherton's public works director, on Wednesday night, Feb. 21.

This story contains 82 words.

If you are a paid subscriber, check to make sure you have logged in. Otherwise our system cannot recognize you as having full free access to our site.

If you are a paid print subscriber and haven't yet set up an online account, click here to get your online account activated.

Comments

Like this comment
Posted by Andrea Gemmet
Almanac staff writer
on Feb 28, 2007 at 12:36 pm

Andrea Gemmet is a registered user.

However, there's still plenty more roadwork to be done on Valparaiso. Once Atherton's project is done, Menlo Park can start its project on the south side of Valparaiso, said Mr. Jones.

Atherton's contractor has an end date of March 7, but each rain day extends the contractor's time by one day, he said.

Once Menlo Park's work wraps up, probably sometime this summer, Atherton and Menlo Park have a joint project to place an asphalt overlay over the entire road, eliminating those lumpy seams that run down the center of Valparaiso.

The reason for the tag-team approach? The border between Atherton and Menlo Park runs right down the center of most of Valparaiso.