Woodside nears the end of $2M bridge project

Worker Jose Flores clears debris from under the Portola Road Bridge in Woodside on Sept. 30, 2021. Photo by Magali Gauthier.

A project this fall to reconstruct the aging Portola Road bridge in Woodside to make it safer is nearing completion.

The construction of the new 81.5-foot-long by 30-foot-wide concrete bridge, located on Portola Road, about 3 miles south of central Woodside and 0.3 miles southeast of Woodside and La Honda roads, will cost about $1.97 million, according to an April report from town staff. The federal government is paying for 88.5% of project costs, while the town is covering 11.5%, staff said.

The project, which began in June, is slated for completion between the end of October and end of November, said Public Works Director Sean Rose in an email. Traffic is closed to one of the bridge's two lanes during construction, and a temporary traffic signal has been installed.

"The existing bridge, constructed in 1914, is in poor condition, and is considered 'functionally obsolete' due to the narrow width of the roadway and the bridge, and the lack of standard bridge rails and approach railings," according to a town staff report from 2020. The bridge carries traffic over Alambique Creek, a seasonal stream.

The alignment of the bridge's north approach does not meet federal standards for a bridge with 3,000 vehicle crossings a day, officials told The Almanac in 2014. A report by Caltrans found that parts of the concrete had deteriorated from the bridge.

What's local journalism worth to you?

Support Almanac Online for as little as $5/month.

Join

The new bridge includes two 10-foot-wide lanes, a 5-foot-wide eastbound sidewalk, an about 2-foot-wide westbound shoulder and concrete barriers on both sides.

The bridge abutments are remaining in place to make sure the existing stream flow is not affected, the report states.

Stay informed

Get the latest local news and information sent straight to your inbox.

Stay informed

Get the latest local news and information sent straight to your inbox.

Follow AlmanacNews.com and The Almanac on Twitter @almanacnews, Facebook and on Instagram @almanacnews for breaking news, local events, photos, videos and more.

Woodside nears the end of $2M bridge project

by / Almanac

Uploaded: Tue, Oct 19, 2021, 10:44 am

A project this fall to reconstruct the aging Portola Road bridge in Woodside to make it safer is nearing completion.

The construction of the new 81.5-foot-long by 30-foot-wide concrete bridge, located on Portola Road, about 3 miles south of central Woodside and 0.3 miles southeast of Woodside and La Honda roads, will cost about $1.97 million, according to an April report from town staff. The federal government is paying for 88.5% of project costs, while the town is covering 11.5%, staff said.

The project, which began in June, is slated for completion between the end of October and end of November, said Public Works Director Sean Rose in an email. Traffic is closed to one of the bridge's two lanes during construction, and a temporary traffic signal has been installed.

"The existing bridge, constructed in 1914, is in poor condition, and is considered 'functionally obsolete' due to the narrow width of the roadway and the bridge, and the lack of standard bridge rails and approach railings," according to a town staff report from 2020. The bridge carries traffic over Alambique Creek, a seasonal stream.

The alignment of the bridge's north approach does not meet federal standards for a bridge with 3,000 vehicle crossings a day, officials told The Almanac in 2014. A report by Caltrans found that parts of the concrete had deteriorated from the bridge.

The new bridge includes two 10-foot-wide lanes, a 5-foot-wide eastbound sidewalk, an about 2-foot-wide westbound shoulder and concrete barriers on both sides.

The bridge abutments are remaining in place to make sure the existing stream flow is not affected, the report states.

Comments

There are no comments yet. Please share yours below.

Post a comment

In order to encourage respectful and thoughtful discussion, commenting on stories is available to those who are registered users. If you are already a registered user and the commenting form is not below, you need to log in. If you are not registered, you can do so here.

Please make sure your comments are truthful, on-topic and do not disrespect another poster. Don't be snarky or belittling. All postings are subject to our TERMS OF USE, and may be deleted if deemed inappropriate by our staff.

See our announcement about requiring registration for commenting.