Read the full story here Web Link posted Wednesday, August 15, 2018, 12:00 AM
Town Square
Civic center cost-cutting on Atherton council agenda
Original post made on Aug 14, 2018
Read the full story here Web Link posted Wednesday, August 15, 2018, 12:00 AM
Comments (1)
a resident of Atherton: Lindenwood
on Aug 14, 2018 at 4:09 pm
Peter Carpenter is a registered user.
The Town Manager states:
" In May 2018, the bid climate proved spectacularly higher than anticipated and the number of pre-qualified bidders that opted to bid on the project dwindled to 2, with the remaining 5 dropping out because they were just simply too busy. The lower bid of the two submitted was nearly 40% higher than the base estimates for the project."
And since then almost 1500 structures in Northern California have been destroyed by fire and, as a result, construction costs will surge even higher for at least the next two years.
Web Link
"A survey from the Associated General Contractors of America showed that 75% of West Coast firms were struggling to fill construction positions, up from 71% in 2016. The shortage comes as California added nearly 50,000 construction jobs in the period of July 2016 to July 2017, with 34,000 projects in the Southern California region. That was two months before the fires began."
And that was before 2018's even more devastating fires.
I predict that ANY plan put out to bid by the Town will result in bids in excess of $50 million - IF anybody even responds to the RFP.
Peter
Don't miss out
on the discussion!
Sign up to be notified of new comments on this topic.
Post a comment
Stay informed.
Get the day's top headlines from Almanac Online sent to your inbox in the Express newsletter.
New artisanal croissant shop debuts in Santa Clara
By The Peninsula Foodist | 3 comments | 3,785 views
Marriage Interview #17: They Renew Their Vows Every 5 Years
By Chandrama Anderson | 11 comments | 2,041 views
Tree Walk: Edible Urban Forest - July 8
By Laura Stec | 5 comments | 1,352 views