Caltrain construction Nov. 9

Original post made by Andrea Gemmet, Almanac staff writer, on Nov 6, 2008

Caltrain announces the following maintenance work affecting Menlo Park and Atherton:

Beginning Sunday, Nov. 9, Caltrain will receive the first of 12 shipments of ballast, or railroad rock. The ballast will be delivered on a 40-car train that will be unloaded near Chilco Street in Menlo Park. It will be stored there and used for ongoing maintenance and future construction projects. After the cars are unloaded they will be temporarily stored on a siding near Marsh Road. 

Caltrain anticipates undertaking a similar unloading exercise about every two weeks for the next six months. 

To minimize the impact to the neighbors, work will be done weekdays from 7 a.m. to 5 p.m.  In addition to the noise from the ballast being unloaded, there will be noise from idling engines and from the empty cars traveling from the Chilco Street site to the Marsh Road siding. 

Comments

Sorry, but further commenting on this topic has been closed.

Burger chain Shake Shack to open in Palo Alto
By Elena Kadvany | 16 comments | 4,674 views

The Cost of Service
By Aldis Petriceks | 1 comment | 1,111 views

Couples: When Wrong Admit It; When Right; Shut Up
By Chandrama Anderson | 0 comments | 567 views

One-on-one time
By Cheryl Bac | 0 comments | 474 views